Approvals for sports courts in every state and territory

Which approvals a court needs, how high a fence can be before you need a permit, and how long councils have to decide. Taken from each state's planning department, building regulator and legislation.

Checked 22 Nov 2026NSWQLDVICWASATASACTNT

Fence height without council approval

Tennis Australia specifies a baseline fence of 3.0 or 3.6 m[1]. In the six states and territories that set a fixed height, a fence is exempt from approval only up to 1.8 to 2.1 m. Victoria is the exception for building approval: a chain-wire tennis court fence does not need a building permit there[2]. In the Northern Territory the limits are in Building Note 114[3].

Fence height allowed without building approvalNew South Wales 1.8 m, Queensland 2.0 m, South Australia 2.1 m, Tasmania 2.1 m, Western Australia 1.8 m, ACT 1.8 m. A tennis court baseline fence is 3.0 or 3.6 m.0 m1 m2 m3 m4 mTennis baseline fence 3.6 mor 3.0 m1.8 mNew South Wales2.0 mQueensland2.1 mSouth Australia2.1 mTasmania1.8 mWestern Australia1.8 mACT
Side and rear fences in residential areas. Victoria and the Northern Territory are not shown because their rule is not a single height.

Council approval rules, state by state

Most court projects need two separate approvals: planning approval for the use and its impact on neighbours, and building approval for the structures. Names and decision times differ by state.

New South Wales

NSW
Planning
Development application (DA) to council. Some minor work is exempt or complying development under the state Codes SEPP.
Building
Construction certificate or complying development certificate.
Fence without building approval
1.8 m for side and rear fences in residential zones, 1.2 m if masonry[4].
Decision time
40 days, or 60 for integrated or designated development. After that the DA counts as refused and you can appeal[5].
Check: NSW Planning Portal, Spatial Viewer

Queensland

QLD
Planning
Development application to council, where the council planning scheme makes the work assessable.
Building
Building approval (development permit for building work)[6].
Fence without building approval
2 m, not counting pool fencing. The council planning scheme can still require approval[7].
Decision time
35 business days for the council decision under the Development Assessment Rules[8].
Check: Business Queensland: when you don't need approval

Victoria

VIC
Planning
Planning permit from council, where the planning scheme requires one. Small proposals can use VicSmart.
Building
Building permit from a registered building surveyor.
Fence without building approval
A chain-wire tennis court fence needs no building permit. Timber side and rear fences up to 2 m, 1.5 m within 3 m of a street[2].
Decision time
60 statutory days for a planning permit, then you can ask VCAT to decide[9]. VicSmart: 10 working days[10].
Check: Building and Plumbing Commission

Western Australia

WA
Planning
Development approval from the local government, unless the local planning scheme exempts the work.
Building
Building permit, certified by a private building surveyor or uncertified and checked by the local government.
Fence without building approval
1.8 m for non-masonry fences, 0.75 m for masonry, where there is no local fencing law[11].
Decision time
60 days for development approval, 90 if advertised[12]. Building permit: 10 business days certified, 25 uncertified[13].
Check: Building and Energy WA

South Australia

SA
Planning
Development approval through PlanSA, made up of planning consent and building consent.
Building
Building consent, part of the same development approval.
Fence without building approval
Approval needed above 2.1 m, or above 1 m for masonry[14].
Decision time
Planning consent: 5 business days if deemed to satisfy, 20 if performance assessed without notification or referral[15]. If the time runs out you can serve a deemed consent notice[16].
Check: PlanSA: find out if you need approval

Tasmania

TAS
Planning
Planning permit from council under the Tasmanian Planning Scheme, for permitted or discretionary development.
Building
Building work is low risk, notifiable or permit work. Low risk work needs no permit[17].
Fence without building approval
2.1 m for non-masonry fences, 1.2 m for masonry[18].
Decision time
28 days for a permitted application, 42 days for a discretionary one[19].
Check: CBOS: categories of building work

Australian Capital Territory

ACT
Planning
Development application to the Territory Planning Authority, unless the work is exempt.
Building
Building approval (BA).
Fence without building approval
1.8 m above ground, not counting pool enclosures[20].
Decision time
30 working days, 45 if a representation is made, 60 for significant development[21]. Public notice runs 15 working days[22].
Check: ACT Planning: check if you need a DA or BA

Northern Territory

NT
Planning
Development permit from the Development Consent Authority, or from the Minister outside its divisions.
Building
Building permit, needed only inside building control areas[23].
Fence without building approval
Exempt fences are listed in Building Note 114[3].
Decision time
About 8 weeks for a development permit. Public exhibition runs 7, 14 or 28 days[24].
Check: NT Government: development applications
Planning tools

Check your site before you call a builder

Padel courts

A padel court is enclosed by walls 3 m high with metal mesh up to 4 m at the ends[25], so it passes the exempt fence height in every state that sets one. Recent padel projects went through a development application: the City of Newcastle approved one for courts at Beresfield Golf Course[26], Parramatta City Council received one for four courts in Lidcombe[27], and the City of Nedlands advertised one for courts at a bowling club[28]. See the padel court guide for size and cost.

Floodlights

Plan on a separate planning application for court lighting. In the council records we checked, lights were assessed on their own: Northern Beaches Council in NSW handled four 7 m light poles as a development application[29]. Holdfast Bay in South Australia assessed court lights on poles up to 12 m as performance assessed development[30]. The Shire of Peppermint Grove in WA requires development approval and a building permit for tennis court lighting[31].

Before you applyCouncils usually look at light spill onto neighbouring homes and the hours of use. Ask your lighting supplier for a light spill plan before you apply.

Shade structures

In NSW a shade structure can be exempt development if it is no higher than 3 m, sits behind the building line, and is at least 900 mm from each boundary in most zones[32]. Other states set their own limits, and some councils differ from each other. Check with your council before you buy.

How we keep this page current

Every rule on this page comes from a state planning department, building regulator, legislation or a council document. We check each source once a month and show the date at the top. If a rule changes, the state card is updated and marked.

Sources

All links checked 22 Nov 2026. We show a figure only with three independent sources or one official source.

  1. [1]Tennis Australia, Fencing and shelters
  2. [2]Building and Plumbing Commission Victoria, Landscaping
  3. [3]NT Government, Garden shed, carport, fence or shade structure without approval
  4. [4]NSW Planning, Fences as exempt development
  5. [5]Land and Environment Court of NSW, deemed refusal periods
  6. [6]Fraser Coast Regional Council, Building approval requirements
  7. [7]Business Queensland, When you don't need building approval
  8. [8]Queensland Government, Amendments to the Development Assessment Rules
  9. [9]Planning Victoria, VicSmart guide
  10. [10]Moira Shire Council, How long does a planning permit take
  11. [11]Shire of Mundaring, Do I need a building permit
  12. [12]City of Stirling, Application timeframes
  13. [13]Building and Energy WA, Processing applications
  14. [14]District Council of Grant, Checklist for fences
  15. [15]PlanSA, Assessment stages and timeframes
  16. [16]Clare and Gilbert Valleys Council, Assessment timeframes in the new planning system
  17. [17]Consumer, Building and Occupational Services, Categories of building work
  18. [18]Devonport City Council, Fences
  19. [19]Tasmanian State Planning Office, Permits
  20. [20]ACT Planning, Fences and freestanding walls
  21. [21]ACT Legislative Assembly, Answer on development application timeframes
  22. [22]ACT Planning, After you apply
  23. [23]NT Government, Work that requires permits
  24. [24]NT Government, Apply for a development permit
  25. [25]International Padel Federation, Rules of Padel 2026
  26. [26]Australasian Leisure Management, Beresfield Golf Course to add padel courts, Nov 2026
  27. [27]PlanningAlerts, 10 Carter Street Lidcombe: 4 padel courts, Parramatta City Council
  28. [28]City of Nedlands, DA25-106002 padel courts at Dalkeith-Nedlands Bowling Club
  29. [29]Northern Beaches Council, DA 236/2009, tennis court lighting on four 7 m poles
  30. [30]City of Holdfast Bay, Panel report on tennis court lights, 2022
  31. [31]Shire of Peppermint Grove, Tennis court lighting
  32. [32]NSW Planning, Shade structures as exempt development